The following inspections must be completed before you may receive a rough
inspection
- Footing - 24’’ deep 3" wider than the block on both sides
- Footing- footings on all pier and post including decks also placement of
deck post before the area around the post has been filled in must be
inspected
- Foundation- to include wall pours if required with steel and foundation
water proofing steel must be placed to meet requirements of the building
code or design and inspected before the wall is poured
- Foundation drain- to include 2" gravel under drain 4" to top of
pipe 6" over drain and silt screen or other approved drain
- Electrical in slab
- Plumbing in Slab if to be done before rough in all lines to be tested
- Slab if to be done before rough in to include termite treatment if
residential to have 4" of stone and 6 mil vapor barrier
- Chimney fireplace
- Rough in inspection can all be done at one time or one at a time to
include framing, rough plumbing including test on dwv and water lines, rough
electrical, rough mechanical, and other inspections that may be required at
this time
All the above and the following inspections must be complete be for you
receive a final
- Insulation to include areas to be covered by sheet rock
- Gas pipe test
- Final to include building, electrical, plumbing, mechanical these can all
be done at one time or one at a time
If all the above inspections have not be completed then a C.O. will not be
issued, the computer is to be programmed so that if these inspections are not in
order then it will not allow and inspection to be printed out.
This is not a complete list of inspections but is a list to help you know
what is required you may need and what other inspections all you have to do is
call.